Construction Progress Summary – March 3, 2026
Booster Station / Transmission Main / Bulk Fill Station
• Transmission Main and Booster Station construction are complete.
• Finish grading at the Booster Station will be completed soon.
• Haynes to be onsite Thursday at 8:30 AM for Hi-Tide system onboarding with city and La Cygne representatives.
• Mike Page will manage the Hi-Tide system and coordinate with La Cygne.
• City received KDHE permit for the water tower on March 2.
• Bulk Fill Station will be ready once Flow Point contract and software setup are complete; contracts are with the City Attorney.
• POA requested a longer fill hose; Mike Page will pursue options.
• Discussion continues on whether the new fill station must remain open 24/7; potential operational conflicts noted.
• Once finish grading is complete and the fill station is operating, Section A of the contract can be closed out.
Distribution Lines
• Updated Construction Progress Map included with minutes.
• Work ongoing on Lines E, F-4, P, Q, and connection at Ullery Rd & E 2400th Rd.
Connection to Existing Linn Valley System
• Connection can be made at Line D (Rose Marie Dr).
• Existing treatment facility expected to remain open until March 2027.
• BG to coordinate timing with POA, Linn Valley, and La Cygne.
• Hettinger responsible for connection means/methods and water quality.
Camper Lots
• City may exempt non-full-time camper residents from meter ordinance and possibly remove some camper lots from the project.
• Council member Hemphill will verify which lots have campers.
• USDA contract requires a minimum number of installed meters based on 830 units.
• Aaron will attend March 9 council meeting to discuss this and Change Order #2.
Meters
• Hettinger has started replacing Linn Valley meters, but some locations missing or not on the removal list. Coordination with Maintenance Supervisor underway.
• BG researching whether new lids are required for swapped meters.
• Meters for new lines will be installed soon.
• City instructed Hettinger not to install meters on camper lots pending council decision.
Change Order #2
• BG and Hettinger recommending adding 19 flush hydrants at dead-end lines to improve system maintenance.
• Will be presented at March 9 council meeting; already sent to USDA-RD.
Payments
• Pay App #8 approved in February.
• Pay App #9 expected soon for March 9 approval.
Field Issues
• Hettinger notified about spoil piles requiring removal; hauling to be done ASAP.
• Complaints about muddy roads; roads are being scraped but cannot be fully cleaned until line installation ends in those areas.
Schedule
• Overall progress estimated at 43% as of Jan 31, 2026 (Pay App #8).
• Transmission Main/Booster/Fill Station milestone billed at 98%.
• Distribution Main milestone 34% billed.
Other
• No additional quality or work-standards issues discussed.